Assignment Name:
Dual Carriageway Projects from Tando Muhammad Khan to Sujawal, and Hyderabad to Tando Ghulam Ali (under PPP mode)
Country:

Pakistan

Location within Country:

Tando Muhammad Khan, Sujawal, Hyderabad and Tando Ghulam Ali

Name of Client:

Works and Services Department, Government of Sindh (GoS)

Completion Date:

Ongoing

Name of Associated Consultants, if any:

Exponent Engineers as Lead Firm, with IQ Capital, RIAA Barker and GEMS

Narrative Description of Project:

The Works & Services Department, Government of Sindh (the ‘Procuring Agency’) has conceived projects for the development of dual carriageways from Tando Muhammad Khan to Sujawal (via Bulri Shah Kareem), 80.7 KM length, and Hyderabad to Tando Ghulam Ali (via Shaikh Bhirkio, Gulab Leghari), 68.4 KM length, (the ‘Projects’) in line with its strategic objectives to strengthen road traffic safety, to improve service level affected by inadequate capacities, and to create better transport infrastructure linkages between the urban and rural economies in a sustainable manner. Procuring Agency wants to conduct feasibility studies and provide advisory and support services in relation to the development of the Projects.

Description of Actual Services Provided by Our Staff within the Assignment:

1. Conduct technical, financial, legal due diligence relating to the Projects; 2. Review Sindh provincial road improvement project and related studies; 3. Review existing roads alignments and perform surveys relating to drainage (manually & through drones), topographic, existing infrastructure (bridges, culverts, drains, retaining walls, etc.) and pavement structure, traffic, utilities, socio-economic and environmental, and customers (road users) willingness and capacity to pay; 4. Outline design parameters covering all the facilities and propose viable options along with features after ground appraisals of Projects’ locations following the industry’s best practices and other applicable standards; 5. Prepare land acquisition folder(s) along with the assessment of land compensation amount in line with relevant rules and policies, as applicable; 6. Prepare utilities folder(s) along with estimated relocation/ strengthening of existing utilities in coordination with the relevant utility stakeholders; 7. Prepare the Projects detailed plans based on the feasibility assessments; 8. Analyze the PPP options with an assessment of various structuring choices and risk allocation matrixes and recommend the most feasible option; 9. Prepare and deliver presentations and reports on the Projects-related documents before the PPP Policy Board and any other forum for seeking approvals as required under the SPP Rules and Sindh PPP Act, 2010; 10. Prepare bidding documents for solicitation of bids from private party(ies) under the preferred PPP mode(s) in accordance with the SPP Rules; and 11. Perform the tasks identified and described in the RFP Document while maintaining close collaboration with the Projects key stakeholders, mainly the Procuring Agency, at all stages of the contract management.

Scroll to Top